Skip to content Commonwealth of Australia Coat of Arms Parliament of Australia - Joint CommitteePhoto of a Committes Meeting
HomeSenateHouse of RepresentativesLive BroadcastingThis Week in Parliament FindFrequently asked questionsContact



Joint Standing Committee on Public Works
Committee activities (inquiries and reports)

Redevelopment of Kokoda Barracks, Canungra , Queensland

Print Chapter 3 (PDF 95B) < - Report Home < - Chapter 2 : Appendix A - >

Chapter 3 Issues and Conclusions

Barracks Services
Living In Accommodation (LIA)
Medical Centre
Childcare Facilities
Sewage Treatment
Power Supply
Building Design
Climatic Considerations
Roofing
Air-conditioning
Workstation Size
Removal of Asbestos
Heritage Considerations
Traffic Management

Barracks Services

Living In Accommodation (LIA)

3.1

Defence’s main submission stated that forty percent of the total project budget estimate would be allocated to works associated with living-in accommodation and messing.1 The Committee requested further detail on the breakdown of number of rooms, both new and refurbished, for LIA.

3.2

Defence informed the Committee that there are currently 460 LIA rooms and 58 day rooms at Canungra. After redevelopment there would be a total of 421 rooms: 415 LIA rooms for trainees and 6 for permanent Other Ranks staff. Of the 421 rooms, 106 would be new and 315 would be refurbished. The area of personal living space of the rooms would range from 14 square metres to 18 square metres.2

Medical Centre

3.3 Defence proposed the Base Medical Centre would receive minor repairs and upgrades, but would not provide in-patient care.3 The Committee sought further detail on the medical facilities at Kokoda Barracks, and what would happen in the case of medical emergency.
3.4

Defence explained that the Base Medical Centre at Kokoda Barracks is for daytime hours, with a medical officer on duty, and is the first port of call for most instances. In case of medical emergency where the Base Medical Centre cannot adequately treat the injury/ailment (or if it is after hours), local/military ambulance transfer the patient to Allamanda hospital. If the particular case is not a medical emergency, the patient is transferred to the military hospital at Enoggera 2 nd Health Support Battalion.4

Childcare Facilities

3.5

In its main submission Defence stated that the existing childcare centre at Kokoda Barracks has sufficient capacity to accommodate the requirements of the staff at the barracks.5 At the public hearing the Committee sought further detail in respect of the childcare facility. Defence informed the Committee that there are two components to the childcare facility:

  • a two day kindergarten (or pre-school in Queensland), for three to four year olds; and
  • three day (Wednesday to Friday) limited hours care for barracks staff.

Some families, who live off-base, also make use of the on-base childcare centre.6

Sewage Treatment

3.6

As stated in Defence’s main submission, part of services infrastructure work for the project includes construction of a new sewage treatment plant.7 The Committee was interested as to the specific reasons Defence had opted not to integrate sewage works with the Beaudesert Shire Council’s plant, as well as the issue of reuse of water.

3.7 Defence explained to the Committee that the existing on-base sewage treatment plant does not meet current standards and building a new on-base sewage treatment plant would satisfy Defence ESD principles and be more cost-effective. Connecting to the Beaudesert Shire Council sewage treatment system would incur a significant increase in cost, and effluent from the barracks would be required to be treated off-base, eliminating future on-site recycling opportunities. The new sewage treatment plant would upgrade the quality of treatment to a contemporary tertiary discharge standard and discharge the effluent into the Coomera River (the same discharge point as the existing plant).8
3.8

Subsequent to the public hearing Defence informed the Committee that ESD principles have been applied to the reuse of water at the base as follows:

  • Water is taken from the established dam on the Coomera River and treated in the Defence water treatment plant (which provides total water use requirements for the Cantonment).
  • Stormwater is diverted into the dam via overground channels, thus can be harvested or added to the environmental flow in the river.
  • All sewage is treated at the Defence sewage treatment plant and discharged below the dam, into the river.

All sewage is treated at the Defence sewage treatment plant and discharged below the dam, into the river.Other proposals for reuse of water such as, the reusing of sewage effluent to irrigate sports fields, is not planned due to high estimated capital costs.9

Power Supply

3.9

At the public hearing, Defence stated that the project was aiming for a 30 year design life allowing for a mid-life upgrade after 15 years.10 The Committee sought confirmation that the power supply to the barracks would be sufficient for the 30 year design life. Defence responded that through continued consultation and correspondence between the Defence regional office and the power supplier, they are confident power requirements of the barracks will be met.11

top  

Building Design

Climatic Considerations

3.10

Defence’s main submission stated that structural design would take account of the highly reactive soils and high level of rainfall of the Canungra area.12 Conscious of the challenges that arise from such climatic conditions, such as the cracking and deteriorating of buildings (as observed on the site inspection), the Committee enquired what measures Defence were undertaking to deal with these issues.

3.11

Defence assured the Committee that there are measures incorporated into building design to exclude water from getting into soil under buildings which can cause cracking and movement. Some specific measures include keeping garden beds away from the edge of buildings and, ensuring the foundation system is stiff enough to manage any unpreventable movement. The design principle would be:

…to have the building move as a whole on effectively a stiff foundation rather than let it articulate and cause differential movement through the building.13

Roofing

3.12

Metal roofing appropriate to the environment was another design feature mentioned in Defence’s main submission.14 The Committee sought more detail on the specific type of roofing material to be used, and the benefits of the particular roofing type. Defence explained that corrugated iron roofing would be used with this project as it is consistent with the heritage of the base, and is widely used with sound results in the Canungra area. The sheeting profile of flatter pitch would be incorporated to allow water to run off whilst minimising chances of leaking through the roof. The expected life of the metal roofing is 30 years, consistent with the overall life 30 year design life of the redevelopment.15

Air-conditioning

3.13

Whilst acknowledging Defence’s awareness of Legionella Bacillus, as outlined in main submission,16 the Committee sought further information on the benefits of the air-conditioning systems to be used in the project. Defence informed the Committee that air-conditioning systems had been chosen specifically for the type of use of the building, citing hours of use and levels of personnel occupation as examples of factors that had been considered.17

3.14

Defence listed examples of types of air-conditioning systems to be used in buildings as follows:

  • Trainee accommodation: bar heaters, fans and natural ventilation.
  • Staff accommodation: chilled air-conditioning (split-units).
  • Office buildings and training facilities: ducted central air-conditioning and external air-cooled cooling plants.

Through the air-conditioning systems chosen, Defence aim to reduce energy use and greenhouse emissions.18

3.15

Defence further explained that Building A1 (a training building) would utilise a system where, during particular climatic conditions, the building would be heated or cooled by breathing as opposed to chilling or heating the air.

Workstation Size

3.16

Plans for Building B2, included in Defence’s main submission,19 outline configuration for workstations. The Committee wished to know whether personnel had been allocated sufficient work space. Subsequent to the hearing, Defence informed the Committee that:

Individual offices are provided at entitlement, nominally 12m 2 …Every staff position identified will be provided with either a desk or workstation in an open-plan environment, using a basic area entitlement of 6.5m 2 per person.20

Personnel who share a position or attend work on a temporary basis, would share the workstation provided for that position.

top  

Removal of Asbestos

3.17

Defence’s main submission explained that the project includes the removal and disposal of about 45 redundant facilities, with all removals/demolition complying with cultural heritage requirements and ESD criteria.21 The Committee sought further detail on the materials that would require removal, and confirmation that any removal would be executed in accordance with relevant codes, standards and Queensland State legislation.

3.18

Defence informed the Committee that 22 of the 45 redundant buildings to be demolished contain asbestos. Buildings to be refurbished would be surveyed prior to construction to ensure asbestos is identified and removed.22

3.19

Defence responded that asbestos, mostly in the form of sheeting in roofs and walls, had been identified as the hazardous material in buildings. Furthermore, Defence assured the Committee that the asbestos would be removed by qualified, licensed and experienced sub-contractors, taking precaution to avoid potentially hazardous situations such as where the asbestos may become airborne. Any removal of asbestos would be arranged to occur within a confined building site, separated from other operations of the base.23

top  

Heritage Considerations

3.20

The high heritage value of Kokoda Barracks was identified in Defence’s main submission.24 The Committee sought further detail on how Defence intended to manage heritage considerations arising from the project.

3.21 A number of informal meetings between Defence and the Australian Heritage Commission (AHC) were held in 2003, with the AHC writing to Defence in September 2003 supporting the draft heritage assessment and concept plans for museum and visitors centre. As concept plans had been revised, a June 2005 heritage impact statement prepared by Environment Resource Management (ERM) addressed the changes and ensured that heritage values were not compromised.25
3.22

Defence reported that an ERM heritage consultant had been contracted to provide a methodology for the identification, recording and rating of buildings which may present heritage concerns. Of the buildings to be demolished:

  • nine have been identified to have moderate heritage value;
  • three are identified to have little heritage value; and
  • the remaining buildings are below the ‘little heritage value’ assessment.26

Subsequent to the public hearing, Defence informed the Committee that the Managing Contractor would source a specialist consultant from the Defence Heritage Panel to conduct the heritage recording prior to demolition in accordance with the Directorate of Heritage Management instruction. In line with changes to Commonwealth heritage legislation, consultation regarding heritage issues is now undertaken with the Department of the Environment and Heritage.27

 

Recommendation 1

The Committee recommends that Defence continue consultation with the Department of Environment and Heritage regarding any heritage issues that may arise from the redevelopment of Kokoda Barracks.

top  

Traffic Management

3.23 The Committee enquired as to what consultation had taken place in respect of the proposed changes to the main entry road to the base, and the benefits of changing the entry/exit point to the base. Subsequent to the hearing, Defence responded that the Beaudesert Shire had no objections to the submitted design, including changes to the Canungra Beachmont Road.
3.24

Defence continued that:

The proposed entry/exit and fencing scheme will provide a safe entry/exit point to the base, circumventing the problems of the past, caused by traffic queuing on the main road to enter the base. This design also improves visitors’ access to the proposed visitors’ centre and museum building and the nearby memorials.28

 

Recommendation 2

The Committee recommends that the proposed redevelopment of Kokoda Barracks, Canungra , Queensland , proceed at the estimated cost of $86.7 million.

 

 

 

HonJudiMoylan MP
Chair
17 August 2005


top

Footnotes

1 Appendix C, Submission No. 1, paragraph 55 Back
2 Letter from Brigadier Peter Hutchinson , Director General, Infrastructure Asset Development, 26 July 2005 Back
3 Appendix C, Submission No. 1, paragraph 30 Back
4 Appendix D, Official Transcript of Evidence, page 4 Back
5 Appendix C, Submission No. 1, paragraph 64 Back
6 Appendix D, Official Transcript of Evidence, page 10 Back
7 Appendix C, Submission No. 1, paragraph 24a Back
8 Appendix D, Official Transcript of Evidence, page 5 Back
9 Letter from Brigadier Peter Hutchinson , Director General, Infrastructure Asset Development, 26 July 2005 Back
10 Appendix D, Official Transcript of Evidence, page 6 Back
11 ibid, page 11 Back
12 Appendix C, Submission No. 1, paragraph 72 Back
13 Appendix D, Official Transcript of Evidence, page 6 Back
14 Appendix C, Submission No.1, paragraph 72 Back
15 Appendix D, Official Transcript of Evidence, page 6 Back
16 Appendix C, Submission No. 1, paragraph 67 Back
17 Appendix D, Official Transcript of Evidence, page 6 Back
18 ibid, page 7 Back
19 Appendix C, Submission No. 1, Attachments 2 and 3 Back
20 Letter from Brigadier Peter Hutchinson , Director General, Infrastructure Asset Development, 26 July 2005 Back
21 Appendix C, Submission No. 1, paragraph 35 Back
22 Letter from Brigadier Peter Hutchinson , Director General, Infrastructure Asset Development, 26 July 2005 Back
23 Appendix D, Official Transcript of Evidence, page 8 Back
24 Appendix C, Submission No. 1, paragraph 47-48 Back
25 Appendix D, Official Transcript of Evidence, page 10 Back
26 ibid Back
27 Letter from Brigadier Peter Hutchinson , Director General, Infrastructure Asset Development, 26 July 2005 Back
28 Letter from Brigadier Peter Hutchinson , Director General, Infrastructure Asset Development, 26 July 2005 Back

Print Chapter 3 (PDF 95KB) < - Report Home < - Chapter 2 : Appendix A - >

top