![]() ![]() ![]() ![]() |
|||
|
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Print Chapter 3 (PDF 182KB) | < - Report Home < - Chapter 2 : Appendix A - > |
Amendments to the Statement of Evidence
Project Funding
Project Scope
Refurbishment of Existing Buildings at Gallipoli Barracks, Enoggera
Living in Accommodation Review
Requirement to Live On-base
Project delivery
Public Private Partnership
Confidential briefings
Project implementation
Experience with Public Private Partnerships
Consultation
Indigenous groups
Local Councils
Defence Personnel
Amendments to the Statement of Evidence |
|
| 3.1 | At the public hearing held on 11 August 2006, Defence provided several amendments to its statement of evidence. These addressed matters concerning project funding, project scope and a comparison of newly constructed buildings against the refurbishing of existing buildings at Gallipoli Barracks, Enoggera, Queensland.1 |
Project Funding |
|
| 3.2 | Defence amended paragraph 9 of its submission by replacing “Current approved phasings are”2 with “Original approved phasings were”.3 This amendment reflected changes in project timing which were discussed at the public hearing held on 29 June 2006.4 |
| 3.3 | A new paragraph 10 was inserted into the statement of evidence, which addressed the original budget for Single LEAP, and provided further details of each phase of the project. Sixty rooms at Robertson Barracks and Kokoda Barracks have already been funded; phase one will provide 1,295 rooms; and phase two will deliver approximately 5,100 rooms. The Expression of Interest (EOI) for phase 2 is expected to be released “later in 2006”.5 |
| 3.4 | The original paragraph 10 was renumbered 10A. The amendment added that
|
Project Scope |
|
| 3.5 | Defence amended paragraph 29 to inform the Committee that
|
Refurbishment of Existing Buildings at Gallipoli Barracks, Enoggera |
|
| 3.6 | The Committee heard that some existing LIA accommodation at Gallipoli Barracks, which were not a part of Project Single LEAP, had recently undergone some minor refurbishment. Defence were questioned whether a cost analysis had been undertaken on refurbishing the existing buildings as opposed to demolishing and rebuilding new accommodation.8 |
| 3.7 | Defence answered these questions by inserting a new paragraph 45A into its statement of evidence, citing a cost-benefit analysis which found that
|
| 3.8 | Defence stated that they would use transit and trainee accommodation as a transit plan for ADF personnel displaced when the current buildings were demolished.10 |
Asbestos |
|
| 3.9 | The Committee heard that 175 buildings within the Gallipoli Barracks contained asbestos in the form of cement sheeting for walls, linings and vinyl tiles. The Committee was assured that this would be removed and disposed of during the demolition of the buildings.11 |
Recommendation 1
|
|
Living in Accommodation Review |
|
| 3.10 | Defence submitted that a 2003 review of all LIA found a shortfall of approximately 26,000 bed-spaces for MWODs.12 At the public hearing held on 29 June 2006, Defence clarified that this figure included all existing accommodation at LIA level 3 and 5 standards, as well as “accommodation for operational surge – the bunk style of accommodation”.13 |
| 3.11 | Project Single LEAP will partially address the shortfall identified in the review, providing approximately 6400 rooms at LIA 5 standard. The 1,295 rooms to be delivered under phase one of the project will be supplemented by about 5,100 rooms “through a second PPP arrangement as part of phase 2”. The balance of the LIA deficiencies is to be provided through separate Defence initiatives.14 |
Requirement to Live On-base |
|
| 3.12 | Defence explained that the ADF personnel required to live in [on-base] included
|
| 3.13 | The Committee queried whether the requirement to live in could be guaranteed, stating that it was a risk that the accommodation would not be required should the policy change within the thirty year period of the project. Defence replied that the sites for phase one were selected on the basis of long-term capability requirements and the reasons for requiring personnel to live on-base were enduring and not likely to change.16 |
| 3.14 | Defence informed the Committee that the rooms could expect to be utilised at an occupancy rate “in the order of 85 per cent”.17 |
Project delivery |
|
Public Private Partnership |
|
| 3.15 | Defence submitted that they proposed to
|
| 3.16 | At the public hearing held on 29 June 2006, Defence explained that this delivery method was appropriate due to the project’s potential size, relative complexity and the “percentage of service component”.19 |
| 3.17 | Phase one of Project Single LEAP was extracted from the larger project on “guidance from the Minister [for Defence] … to test the [PPP] methodology” as phase two of the project would be “much more complex in terms of the geographic spread of the sites as well as the number of units to be constructed”.20 |
| 3.18 | The Committee heard that Defence will pay a monthly service charge to the strategic partner, payable after the facilities are occupied. The charge will be
|
| 3.19 | The Committee queried Defence as to why one strategic partner, rather than three, was to be engaged to develop the three sites. Defence replied that the three sites were packaged together to be “attractive to industry” and that one strategic partner would result in a simpler, single national contract.22 |
Confidential briefings |
|
| 3.20 | Defence provided the Committee with two commercial-in-confidence briefings. The first was held prior to the 11 August 2006 public hearing and the second on 14 September 2006. |
| 3.21 | At these briefings, Defence provided the Committee with details of the expected costs of the project, as contained in the Public Sector Comparator (PSC). The Committee was told that incoming tenders would be compared to the PSC to ensure that the Commonwealth received value for money. |
Project implementation |
|
| 3.22 | Early in 2006, the Committee approved a request from Defence to progress their procurement strategy in parallel with Committee consideration of the project.23 |
| 3.23 | Defence submitted that EOI were sought in October 2005, with nine formal consortia bids being received. Four consortia were short listed to proceed to the Request for Proposal (RFP) stage, with submissions due in May 2006.24 |
| 3.24 | At the 29 June public hearing, Defence provided an update to the Committee, stating that all four consortia tenders had been received and were undergoing evaluation. Defence informed the Committee that it expected a recommendation on a strategic partner to be made to government later in 2006.25 |
| 3.25 | During the course of the inquiry, the Committee faced the challenge of giving consideration to this project before its final form is known. For example, the design of the facilities26 and the management of environmental matters27 will only be known or addressed once a strategic partner is engaged. |
| 3.26 | The Committee recognises that this is a unique feature of PPPs but requests a briefing from Defence on the final form and costs of the project. |
Recommendation 2
|
|
Recommendation 3
|
|
Experience with Public Private Partnerships |
|
| 3.27 | The Committee questioned Defence on its experience in coordinating PPPs. Defence responded by saying that they
|
Consultation |
|
Indigenous groups |
|
| 3.28 | At the 29 June 2006 public hearing, the Committee questioned Defence about the level of consultation undertaken with indigenous groups at each of the sites. Defence stated that they had consulted with the land council responsible for the Holsworthy area, have “undertaken an initial cultural and heritage assessment” and will invite the lands council to assist them with further cultural assessments.29 |
| 3.29 | At the public hearing held on 11 August 2006, Defence indicated that they had engaged the Jagera people at RAAF Base Amberley and were in the process of engaging the Tharawal people at Holsworthy.30 |
Recommendation 4
|
|
Local Councils |
|
| 3.30 | The submission of the Ipswich City Council was supportive of the proposal at RAAF Base Amberley.31 When representatives of the Council appeared before the Committee, they stated that they were happy with the level of consultation undertaken by Defence.32 |
| 3.31 | In response to a question on what discussions were undertaken with councils local to the Holsworthy site, Defence stated that the Liverpool City Council and the Sutherland Shire Council were both briefed on the project and neither raised specific issues.33 |
Defence Personnel |
|
| 3.32 | The Committee asked whether Defence personnel had an opportunity to have an input into the project. Defence stated that
|
Recommendation 5
|
|
Hon Judi Moylan MP |
|
| 1 | Appendix E, Official Transcript of Evidence, 11 August 2006, pages 2 and 3 Back |
| 2 | Appendix C, Submission No. 1, paragraph 9 Back |
| 3 | Appendix E, op cit, page 3 Back |
| 4 | Appendix D, Official Transcript of Evidence, 29 June 2006, page 11 Back |
| 5 | Appendix E, Official Transcript of Evidence, 11 August 2006, page 3 Back |
| 6 | ibid, page 3 Back |
| 7 | ibid, page 3 Back |
| 8 | Appendix D, op cit, page 5 Back |
| 9 | Appendix E, op cit, page 2 Back |
| 10 | Appendix D, op cit, page 12 Back |
| 11 | ibid, page 10 Back |
| 12 | Appendix C, op cit, paragraph 8 Back |
| 13 | Appendix D, op cit, page 13 Back |
| 14 | Appendix E, op cit, page 3 Back |
| 15 | Appendix D, op cit, pages 12 and 13 Back |
| 16 | Appendix E, op cit, pages 5 to 7 Back |
| 17 | ibid, page 4 Back |
| 18 | Appendix C, op cit, paragraph 76 Back |
| 19 | Appendix D, op cit, page 6 Back |
| 20 | ibid, pages 10 and 11 Back |
| 21 | Appendix D, op cit, page 7 Back |
| 22 | ibid, page 11 Back |
| 23 | ibid, page 2 Back |
| 24 | Appendix C, op cit, paragraph 16 Back |
| 25 | Appendix D, op cit, pages8 and 9 Back |
| 26 | Appendix E, op cit, page 10 Back |
| 27 | Appendix D, op cit, page 14 Back |
| 28 | ibid, page 5 Back |
| 29 | Appendix D, op cit, page 15 Back |
| 30 | Appendix E, op cit, page 3 Back |
| 31 | Volume of Submissions, Submission No. 2, page 1 Back |
| 32 | Appendix D, op cit, pages 18 and 19 Back |
| 33 | Appendix E, op cit, page 10 Back |
| 34 | ibid, page 10 Back |
| Print Chapter 3 (PDF 182KB) | < - Report Home < - Chapter 2 : Appendix A- > |
![]()