![]() ![]() ![]() ![]() ![]() ![]() |
|||
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|||
![]() |
|
Navigation: Previous Page | Contents | Next Page Chapter 4 Proposed redevelopment of the Australian Defence Force Academy, Canberra, Australian Capital Territory.4.1 The proposed redevelopment of the Australian Defence Force Academy (ADFA) aims to update and extend existing facilities, and provide new facilities, which will meet the needs of ADFA for coming decades. 4.2 The proposal was referred to the Committee on 23 March 2011. Conduct of the Inquiry4.3
The inquiry was advertised in The Australian newspaper. The
Committee received one submission, and one confidential supplementary
submission detailing the project costs. A list of submissions can be found at 4.4 The Committee undertook a site inspection, public hearing and an in-camera hearing on the project costs on 3 June 2011 in Canberra. 4.5 The transcript of the public hearing as well as the submissions to the inquiry are available on the Committee’s website.[1] Plans for the proposed works are detailed in submission 1: Department of Defence (Defence). Need for the works4.6 The submission from Defence states that the works are necessary in order to ensure that the facilities meet the education and training needs of ADFA, particularly given changes in teaching techniques and spatial requirements since its establishment in 1986. In addition, many of the other facilities – administrative, messing, accommodation and physical training – are in need of refurbishment due to their age. 4.7 The Committee finds that there is a need for the works. Scope of the works4.8 The proposed scope of the works is detailed in Submission 1: Defence. The project proposes the following works:
4.9 If Parliamentary approval is given, construction will commence in late 2011 and will be complete by the end of 2014. 4.10 The Committee finds that the proposed scope of works is suitable to meet the needs of the ADFA Redevelopment project. Cost of the works4.11 The total out-turn cost for this project is $98.5 million, excluding GST. The Committee received a confidential supplementary submission detailing the project costs and held an in-camera hearing with Defence on the project costs. 4.12 The Committee is satisfied that the costings for the project provided to it are adequate. Committee comment4.13 Overall, the Committee is satisfied that this project has merit in respect of need, scope and cost. 4.14 Having examined the purpose, need, use, revenue and public value of the works, the Committee considers that it is expedient that the proposed works proceed.
|
![]() |