![]() ![]() ![]() ![]() |
|||
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
FTTP Brownfields |
FTTP Greenfields Build |
FTTP Greenfields BOT |
Satellite First Release |
Wireless |
Total |
|
June 2011 |
13 000 |
- |
45 000 |
165 000 |
- |
223 000 |
|
June 2012 |
132 000 |
7000 |
120 000 |
- |
14 000 |
273 000 |
|
June 2013 |
805 000 |
63 000 |
84 000 |
- |
269 000 |
1 221 000 |
|
Total |
950 000 |
70 000 |
249 000 |
165 000 |
283 000 |
1 717 000 |
Table 2.2 Premises or Lots Passed or Covered (cumulative year-on-year)[13]
|
2012-15 CP Premises or Lots Passed*/Covered YoY |
|||||
|
|
FTTP Brownfields |
Fixed wireless and satellite |
Subtotal brownfields and fixed wireless and satellite |
FTTP Greenfields** |
Total |
|
FY2011 |
18 000 |
165 000 |
183 000 |
- |
183 000 |
|
FY2012 |
29 000 |
174 000 |
203 000 |
10 000 |
213 000 |
|
FY2013 |
286 000 |
320 000 |
606 000 |
55 000 |
661 000 |
|
FY2014 |
1 129 000 |
374 000 |
1 503 000 |
178 000 |
1 681 000 |
|
FY2015 |
2 499 000 |
752 000 |
3 251 000 |
413 000 |
3 664 000 |
|
FY2016 |
3 862 000 |
907 000 |
4 769 000 |
763 000 |
5 532 000 |
*Greenfields in new developments: lots passed may not equal premises passed depending on developer’s timeframe to build.
**FTTP Greenfields are demand-driven activities which are subject to variations in housing starts and Developer activities (supply of new premises and demand from new developers for NBN Co to install fibre).
Table 2.3 Premises with Active Service (incremental year on year)[14]
|
|
FTTP Brownfields |
FTTP Greenfields Build |
FTTP Greenfields BOT |
Satellite First Release |
Wireless |
Total |
|
June 2011 |
- |
- |
35 000 |
- |
- |
35 000 |
|
June 2012 |
5000 |
5000 |
92 000 |
13 000 |
1000 |
116 000 |
|
June 2013 |
255 000 |
55 000 |
64 000 |
20 000 |
25 000 |
419 000 |
|
Total |
260 000 |
60 000 |
191 000 |
33 000 |
26 000 |
570 000 |
Table 2.4 Premises with Active Service (cumulative year on year)[15]
|
2012-15 CP Premises or Lots Passed*/Covered YoY |
|||||
|
|
FTTP Brownfields |
Fixed wireless and satellite |
Subtotal brownfields and fixed wireless and satellite |
FTTP Greenfields* |
Total |
|
FY2011 |
600 |
200 |
800 |
- |
800 |
|
FY2012 |
3000 |
10 000 |
13 000 |
500 |
13 500 |
|
FY2013 |
44 000 |
38 000 |
82 000 |
10 000 |
92 000 |
|
FY2014 |
420 000 |
64 000 |
484 000 |
67 000 |
551 000 |
|
FY2015 |
1 311 000 |
100 000 |
1 411 000 |
204 000 |
1 615 000 |
|
FY2016 |
2 559 000 |
145 000 |
2 704 000 |
477 000 |
3 181 000 |
*FTTP Greenfields are demand-driven activities which are subject to variations in housing starts and Developer activities (supply of new premises and demand from new developers for NBN Co to install fibre).
2.19 The NBN Co 2012-2015 Corporate Plan includes adjustments that have been made in regard to the stated nine month delay in the NBN rollout.[16] The NBN Co outlined these delays and stated:
There were a number of reasons, one of which was the ACCC decision on the points of interconnect. They moved from 14, which we had based our network on and designed it for, to 121. That required a rejig of the network—quite a substantial one. We had anticipated getting the national duct data in June. We got it the following March. Of course, the construction contracts themselves took a bit longer for us to negotiate because we terminated a process and went into a new process to make sure that we get value for money for the Australian taxpayer. I have to also say that the issues we talked about with addresses were also quite a task to undertake. We also took on board, on 1 January 2011, the greenfields requirement—and I have some information because I know the committee is interested in greenfields, but it looks like we are out of time to do that—and that was quite a substantial undertaking.[17]
2.20 The ACCC commented on its role in the consideration of the Telstra
Structural Separation Undertaking (on which the Telstra Agreement relied for
finalisation) and the perception that the ACCC had contributed to the delay in
the NBN rollout commencement. The ACCC stated:
...any delay that I have heard potentially attributed to us was potentially the delay in approving the Telstra structural separation undertaking. That took us six and a half months to approve. My understanding was the original NBN timetable meant that that would all be settled by the middle of 2011. As it happened, it never came to us until the end of July, so we never even had it. To have even approved it in one month would have meant that we would have had to just close our eyes and sign. In fact, because we were trying to get interim equivalence and transparency, it was necessarily a complicated issue. I can understand that NBN were forecasting on the basis of an agreement that actually had to be settled between the ACCC and Telstra. So they may have found that hard to judge. I think the key delay was the negotiations between NBN and Telstra. Our role necessarily was always going to take an amount of time—whether that was four, five, six or nine months. These things do take time. I do not think we contributed to the delay at all.[18]
2.21 The NBN Co clarified the events that lead to the delay in the commencement of the NBN rollout and stated:
We are not suggesting that the ACCC contributed to the delay. We anticipated in December 2010 that we would have reached agreement and could start using the national duct data from Telstra—which we need to do all the things that .... [have been] spoken about—by June 2011. That was probably optimistic. We underestimated the length of time and the complexity of reaching final agreement with Telstra and we also did not anticipate the fact that the deal could not commence until after the Telstra [structural separation undertaking] SSU, nor how long that would take. It did not occur until March [2012], so we could not get the national duct data until then. So we could not do the design process that we talked about earlier.[19]
2.22 The Performance Report, similarly to previous reports included the progress information on the NBN rollout over the period from 1 January to 30 June 2012, in addition to developments contributing to the NBN rollout covering the three month period from 1 July to 1 October 2012.
2.23 The key statistical results for the NBN rollout in the reporting period are listed in Table 2.5. For the purposes of comparison and to facilitate identification of progress, results are presented alongside the NBN Co Corporate Plan 2012-2015 targets.
Table 2.5 Key Results of the National Broadband Network Rollout for the six month period ended on 30 June 2012 (Construction commenced and Premises Passed/Covered)
|
Cumulative Metrics |
NBN Co 2012-2015 Corporate Plan Targets (p. 36) |
Cumulative current half year as at 30 June 2012 |
Cumulative previous half year as at 31 Dec 2011 |
|
Construction Commenced[20] |
|
|
|
|
Brownfields |
|
280 142 |
77 357 |
|
New Development Lots |
|
13 885 |
12 723 |
|
Fixed Wireless and Satellite |
|
7062 |
1952 |
|
Premises passed (PP)/covered |
|
|
|
|
Brownfields |
29 000 |
28 860 |
18 243 |
|
New Development Lots |
10 000 |
10 054 |
951 |
|
Fixed Wireless and Satellite |
174 000 |
173 885 |
165 000 |
|
Total PP (across the three technologies) |
213 000 |
212 799 |
|
Source Shareholder Ministers’ Performance Report, Submission 13, p. 5.
2.24 For Premises passed/covered, the half year results show that the NBN Co achieved for:
2.25 Table 2.5 contains a comparison of the totals (across the three network
technologies) for the six month period ended 30 June 2012 and shows the NBN Co
is just below its total target of premises passed/ covered (213 000), with
212 799 premises covered.[21]
Table 2.6 Key Results of the National Broadband Network Rollout for the six month period ended on 30 June 2012 (Premises Activated)
|
Cumulative Metrics |
NBN Co 2012-2015 Corporate Plan Targets (p. 36) |
Cumulative current half year as at 30 June 2012 |
Cumulative previous half year as at 31 Dec 2011 |
|
Premises Activated (PA) |
|
|
|
|
Brownfields |
3000 |
3364 |
2095 |
|
New Development Lots |
500 |
503 |
110 |
|
Fixed Wireless and Satellite |
10 000 |
9669 |
2197 |
|
Total PA (across the three Technologies) |
13 500 |
13 536 |
|
2.26 As shown in Table 2.6, for Premises Activated, the half year results show that the NBN Co achieved for:
2.27 Comparison of totals (across the three network technologies) for the six month period ended 30 June 2012, shows that while the NBN Co is just below its total target of premises activated for fixed and wireless, overall, the NBN Co has exceeded its target (13 500), with 13 536 premises activated.[22]
2.28 The Government’s Performance Report also includes an update on events that have occurred since the reporting period from 1 July to 1 October 2012.
2.29 The key announcements and events identified in the Performance Report are listed in Table 2.7.
Table 2.7 Key National Broadband Network Rollout Events from 1 July 2012 to 1 October 2012
|
Date (2012) |
Event/Announcement |
|
3 – 12 July |
NBN Co announces local government areas in NSW and Qld to receive fixed wireless services from mid to late 2013 |
|
12 July |
|
|
19 July |
Optus Agreement authorised by ACCC |
|
8 August |
NBN Co’s new Corporate Plan released |
|
9 August |
Opening of expanded Prysmian fibre manufacturing facility in Dee Why, NSW |
|
16 August |
Report released – Operation of the Freedom of Information Act 1982 and its application to NBN Co held documents |
|
24 August |
Ceduna, SA selected as fourth satellite ground station location |
|
4 September |
NBN Co released ‘NBN for Business’ a publication to assist small business ‘to make the most of high speed broadband’ |
|
6 September |
Silcar and Service Stream are announced as the NBN network maintenance and installation providers over the next two years NBN fixed wireless services are made available in Geraldton, WA |
|
19 September |
Opening of NBN Co’s National Contact Centre at Varsity Lakes, Qld |
|
28 September |
|
|
1 October |
Geraldton, Carnarvon and Kalgoorlie, WA selected as location for three new satellite ground stations |
Source Shareholder Ministers’ Performance Report, Submission 13, pp 4-5.
Table 2.8 Deployment Schedule for 2012-2015 Corporate Plan[23]
|
Deployment Schedule from FY 2011 to FY2021 |
|||||||||||
|
June YE |
2011 |
2012 |
2013 |
2014 |
2015 |
2016 |
2017 |
2018 |
2019 |
2020 |
2021 |
|
Brownfields Premises Passed (000’s) |
18 |
29 |
286 |
1129 |
2499 |
3862 |
5168 |
6423 |
7610 |
8879 |
10091 |
|
BF Premises passed Daily Run Rate (250 working days/year) |
73 |
42 |
1028 |
3372 |
5482 |
5450 |
5225 |
5020 |
4746 |
5078 |
4847 |
|
Greenfields Premises Passed (000’s premises) |
- |
10 |
55 |
178 |
413 |
763 |
1111 |
1415 |
1673 |
1904 |
2111 |
|
GF Premises Passed Daily Run Rate (250 working days/year) |
- |
40 |
179 |
492 |
941 |
1400 |
1392 |
1215 |
1033 |
922 |
829 |
|
Fibre Premises Passed (000’s Premises) |
18 |
39 |
341 |
1307 |
2912 |
4625 |
6279 |
7838 |
9283 |
10 783 |
12 202 |
|
Fibre Premises Passed Daily Run Rate (250 working days/year) |
73 |
83 |
1207 |
3864 |
6423 |
6850 |
6617 |
6235 |
5780 |
6001 |
5677 |
|
Brownfields Premises Connected (000’s) |
1 |
3 |
44 |
420 |
1311 |
2559 |
3566 |
4578 |
5468 |
6195 |
6939 |
|
BF Premises connected Daily Run Rate (250 working days/year) |
3 |
11 |
161 |
1504 |
3565 |
4991 |
4029 |
4047 |
3562 |
2908 |
2976 |
|
Greenfields Premises Connected (000’s premises) |
- |
1 |
10 |
67 |
204 |
477 |
775 |
1017 |
1227 |
1412 |
1574 |
|
GF Premises Connected Daily Run Rate (250 working days/year) |
- |
2 |
40 |
227 |
548 |
1092 |
1189 |
968 |
841 |
740 |
649 |
|
Fibre Premises Connected (000’s Premises) |
1 |
4 |
54 |
487 |
1515 |
3036 |
4341 |
5594 |
6695 |
7607 |
8513 |
|
Fibre Premises Connected Daily Run Rate (250 working days/year) |
3 |
13 |
201 |
1731 |
4114 |
6083 |
5218 |
5016 |
4403 |
3648 |
3624 |
|
Fixed Wireless and Satellite Premises Covered (000’s Premises) |
165 |
174 |
320 |
374 |
752 |
907 |
921 |
934 |
948 |
961 |
974 |
|
Fixed Wireless and Satellite Premises Connected (000’s Premises) |
0 |
10 |
38 |
64 |
100 |
145 |
161 |
191 |
206 |
219 |
232 |
|
Total Premises Connected – All Platforms (000’ Premises) |
1 |
14 |
92 |
551 |
1615 |
3181 |
4502 |
5785 |
6901 |
7827 |
8745 |
2.30 Table 2.8 shows the NBN Co’s planned deployment schedule for 2012-2015 for brownfields, greenfields, and fixed wireless and satellite - premises passed, daily run rates, and premises connected.
2.31 By the end of 2012, as shown in Table 2.8, 14 000 premises are planned to be connected across all platforms of the NBN, with this number increasing exponentially to 92 000 by the end of 2013.
2.32 In a statement made in relation to NBN rollout data for the six month period ended on 31 December 2012, the NBN Co stated that it expected NBN rollout to be ‘ramped up’ in the fourth quarter of the 2012-2013 financial year. The NBN Co stated:
The results reflect progress in the early stages of the rollout, and are what we would expect given the time and work necessary to put in place the contracts and agreements needed to get to this point of execution. As can be seen by our targets, this rollout is not a linear progression, but a rapid ramp-up. We are targeting to pass more premises in the final quarter of the financial year than we will have passed in the entire project up to the beginning of that quarter. Additional construction resources will be added over the coming months to help achieve these targets.[24]
2.33 The Shareholder Ministers’ report contains unaudited consolidated financial statements for the NBN Group for the six month period and financial year ended on 30 June 2012.
2.34 As these statements are unaudited they were not accompanied with an auditor’s statement or explanatory notes verifying their non qualification and accuracy respectively.
2.35 When asked about why unaudited financial results instead of audited financial statements were included in the Performance Report, the NBN Co stated:
That is what I would have to refer to the department. This is the Government's report, so I would have to refer it to them.[25]
2.36 The Department of Broadband, Communications and the Digital Economy (DBCDE) subsequently responded that:
The Government's progress reports on the National Broadband Network cover six monthly periods to 30 June and 31 December and are based on information provided by NBN Co.
The financial statements contained within the government's progress reports are not subject to the same auditing arrangements as those applied to annual reports. While NBN Co's annual report had been tabled by the time of the 30 October Joint Committee hearing, preparation of the government's progress report was undertaken separately and was therefore appropriately marked as unaudited.[26]
2.37 In the absence of accompanying explanatory and verification documents, supporting financial information and some information has been taken from the NBN Co 2012 Annual Report and some from the Performance Report.
2.38 Over the six month period the Government provided $350 million in equity funding to the NBN Co.[27] In reference to equity funding provided, the NBN Co Annual Report states:
To the extent that the Commonwealth has provided for equity funding in forward budget estimates, NBN Co has recorded this as expected equity funding in the Schedule of Commitments. The expected equity funding to the company as at 30 June 2012 is $24.668 billion. As at 30 June 2012 a total of $2.832 billion has been made available to the [NBN Co].[28]
2.39 The current Equity Funding Agreement between NBN Co and the Government was capped at $27.5 billion with reference to the NBN Co Corporate Plan 2011-2013. With the release of the 2012-2015 NBN Co Corporate Plan (which contains revised targets), on 8 August 2012, total equity funding was increased by approximately $3 billion to a total of $30.4 billion.[29]
2.40 Over the six month period, the NBN Co experienced an operating loss of approximately $300 million (exact amount is $299 639 000)[30] with an operating loss of approximately $520 million (exact amount is $520 205 000) for the end of the 12-month period.[31] This is approximately $197 million more than for the previous year. Operational expenditure over the 12-month period to 30 June 2012 was attributed to:
2.41 For the 2011-2012 financial year the NBN Co received revenue of approximately $62 million consisting of telecommunications revenue ($1.9 million), other revenue ($19 000) and interest income (approximately $60 million).[38]
2.42 Total expenses increased from the previous year of $355 837 million to $589 052 million.[39]
2.43 When asked how long the NBN Co expects to be in the position of experiencing an operating loss, the NBN Co stated ’that is in the corporate plan; I think it is 2019.’[40]
2.44 The NBN Co explained the operating loss timeframe and stated:
NBN Co’s projected cash flows are typical of large-scale infrastructure projects that require up front capital and operating expenditure to design and construct the network in order to generate revenue streams in future periods. NBN Co’s revenue streams are gradually projected to build up as the network is rolled out and service providers develop their customer base of end-user premises onto the Fibre, Fixed Wireless and Satellite networks. As revenue streams gradually build up, these are projected to exceed Operating expenditure in FY2019.[41]
2.45 The Government’s Performance Report was received by the committee on 23 October 2012.
2.46 In its First Report, the committee recommended that the Government’s six monthly performance report be provided to the committee:
... no later than three months before the committee is due to report to the Parliament.[42]
2.47 Taking into consideration this timeframe, the Government’s Performance Report was due to the committee by the end of September 2012.
2.48 In previous reports there has been substantial discussion about the delay in receiving answers to questions taken on notice by the NBN Co and the DBCDE. In addition, the quality of answers has also been commented on.
2.49 The committee has also commented on the pressure this has placed on it in regard to the timing of its reporting to Parliament. The committee subsequently made recommendations in this regard and has received comment through the Government’s formal responses to reports.
2.50 In an effort to receive answers to questions on notice to supplement the committee’s hearing on 30 October 2012, the committee set an eight day timeframe for receiving answers to questions on notice.
2.51 In correspondence regarding the provision of answers to questions on
notice from the 30 October 2012 hearing the DBCDE stated:
The Department and NBN Co aim to deliver answers to questions
on notice at the earliest opportunity and to the best extent possible will
endeavour to meet the Committee’s deadline. A number of responses have already
been tabled with the Committee, and more will be tabled later tomorrow before
the 14 November 2012 deadline.... We understand that the NBN Co will be in a
position to provide a further 20 responses over the next several days and the
remainder shortly thereafter.
To assist the Committee in preparing its report, NBN Co and the Department have prioritised the questions that are relevant to the performance of the NBN in the review period to June 2013.[43]
2.52 The tabular representation of actual results achieved for the physical NBN rollout contained in the Shareholder Ministers’ performance report is not presented in a format which enables comparison with Corporate Plan targets.
2.53 The committee has previously commented on the type of data that should be included in the Shareholder Ministers’ Performance Report to better enable comparison of data across years in line with published NBN rollout targets.
2.54 In particular, the committee reiterates the statements it made in the Third Report that it ‘does not find it meaningful to be provided with data on how many premises have been passed or premises made active between periods or years without any kind of target or benchmark on which to compare this data.’
2.55 In addition, the NBN Co corporate plan presents targets by financial years (covering the periods from 1 July to 30 June), not in six monthly periods as contained in the Shareholder Ministers’ Performance Report.
2.56 In respect to this issue, the committee expects high levels of accountability and transparency from an organisation that is responsible for the design and build of Australia’s largest ever infrastructure project.
2.57 The committee finds that the Performance Report while providing a general overview of the activities associated with the NBN rollout does not easily show which NBN rollout targets have been met over the six month period. The committee has made a recommendation in regard to this finding.
2.58 The committee has now on several occasions during the course of its reviews heard the reasons why the commencement of the NBN rollout has been delayed. Although it is stated in the new NBN Co Corporate Plan that the NBN rollout was delayed, and the rollout timeframe has been extended by six months, it is uncertain whether the NBN rollout is still subject to delay, and the extent of the impact of the previous delay.
2.59 The ACCC has commented that it was not responsible for any delay to the commencement of the NBN rollout as a result of its consideration of the Telstra SSU. The NBN Co has agreed with comments made by the ACCC in this regard.
2.60 The Performance Report again contains unaudited financial statements with the only accompanying disclaimer-type statement being ‘Unaudited financial statements are presented in the following section. Further information is available in the audited financial statements included in the 2011-12 Annual Report.’[44]
2.61 Without an accompanying auditor’s statement or accompanying explanatory notes, the accuracy of financial statements provided in the Performance Report and whether the financial statements were prepared in accordance with accounting standards, may be questioned. Where accounting standards are not followed to prepare financial statements implies that without such rigour in the process, there is more likely to be resulting errors.
2.62 The DBCDE’s response to the reason for providing unaudited financial statements in the Performance Report is not satisfactory. In particular, the DBCDE’s response states that ‘the financial statements contained within the Government's progress reports are not subject to the same auditing arrangements as those applied to annual reports.’
2.63 To then state in the Performance Report that further information is provided in the NBN Co’s Annual Report is unhelpful as the two are not comparable as they were prepared using different methodologies.
2.64 Given that the NBN Co Annual report was released before the Performance Report was provided to the committee, there would have been no reason not to include it in the Performance Report.
2.65 The committee would prefer to receive audited financial statements so that results are certified and so can be verified, and has recommended this course of action.
2.66 To date, through four reviews, the Government’s Performance Report has not reached the committee within the three month period that the committee recommended in its First Report.
2.67 One week before the committee’s biannual hearing with the NBN Co, originally scheduled for 8 October 2012, the committee had not yet received the Government’s Performance Report.
2.68 The hearing was subsequently rescheduled from 8 October to 30 October 2012 to accommodate witnesses’ schedules. While this timeframe would have provided additional time for the Government’s Performance Report to reach the committee, the Performance Report was not received by the committee until 23 October 2012. This is four working days prior to the 30 October 2012 biannual hearing.
2.69 Receiving the Government’s Performance Report at least three months before it is required to report to the Parliament allows the committee to undertake its oversight role without any initial delay in the review process.
2.70 While the committee appreciates receiving the Government’s Performance Report ahead of its biannual hearing, it would be preferable for the committee to receive the Performance Report at least one month before the biannual hearing with the NBN Co is scheduled to take place. This would assist the committee in fulfilling its reporting and oversight obligations more uniformly.
2.71 Given the short time available for the committee to finalise its report following its rescheduled biannual hearing with the NBN Co and in an effort to receive answers to questions on notice to supplement the committee’s evidence, an eight day timeframe for receiving answers to questions on notice was put in place.
2.72 The committee appreciates that this timeframe was relatively short and appreciates the efforts of the NBN Co and DBCDE to provide answers to questions on notice within this timeframe.
2.73 Receiving answers to questions on notice in this short timeframe has
enabled the committee to meet its reporting obligations and provide more up to
date information on the NBN rollout to the Parliament and interested citizens.
Recommendation 1 |
|
| 2.74 | The committee recommends that the key performance indicator information presented in the Shareholder Ministers’ six-monthly National Broadband Network (NBN) Performance Report list and detail: (1) established Business Plan targets and (2) actual results which track the progress of the NBN rollout over each six month period as well as yearly, to enable the comparison of actual physical NBN rollout results with published NBN Co Corporate Plan targets. |
Recommendation 2 |
|
| 2.75 | The committee recommends that the Shareholder Ministers’ six monthly performance report on the progress of the National Broadband Network rollout include audited financial statements with accompanying explanatory notes, and where it is not possible to provide these in the first instance, that they be forwarded to the Joint Committee on the National Broadband Network when prepared, as an addendum to the Performance Report. |
Recommendation 3 |
|
| 2.76 | The committee recommends that subsequent Shareholder Ministers’ six monthly performance report on the progress of the National Broadband Network rollout be provided to the committee no less than one month before the scheduled biannual hearing with the Joint Committee on the National Broadband Network. |