![]() ![]() ![]() ![]() |
|||
|
|
|
|||||||||
|
1. |
To improve planning for estate maintenance, the ANAO recommends that Defence: (a) bases its estate maintenance planning on technical assessments of the condition of facilities and their usage, as well as continuing to take into account contribution to Defence capability and legislative requirements; (b) undertakes periodic assessments of the condition of engineering services at bases and ranges and proposes any necessary maintenance or alternative remedial action; and (c) having regard to up-to-date data on the condition and usage of its buildings and infrastructure, as well as its overall priorities, reassesses the level of funding allocated to maintain the estate in an economic manner. Defence response: Agree. |
|
2. |
To improve the delivery of maintenance services, the ANAO recommends that the approach to estate maintenance delivery be reviewed to focus on the outputs that Defence requires, and that Defence: (a) undertakes work to develop an improved contracting model for the delivery of estate maintenance, including Risk Managed Works, for the next round of contracts; (b) considers building on its initiatives to have prime contractors undertake low cost general estate works themselves, and separating Risk Managed Works between those best undertaken by the prime contractors and those best delivered as mid level capital works; and (c) develops a change management plan to support the implementation of revised delivery and contracting arrangements. Defence response: Agree. |
4.28 The Joint Committee of Public Accounts and Audit (JCPAA) held a public hearing on Wednesday 21 September 2011, with the following witnesses:
4.29 The Committee took evidence in the following areas:
4.30 The Committee was interested in Defence’s strategy and timeline to implement the ANAO’s recommendations and in particular, how the implementation of the recommendations fit within the wider Defence estate strategy—Force 2030.
4.31 The ANAO made two recommendations to Defence aimed to improve the Department’s planning of estate maintenance and its delivery of maintenance services.
4.32 Defence agreed with the ANAO’s recommendations and are working on an ‘approach and a process’ for implementation. Defence advised the Committee that it will ‘embed’ its activities to execute the ANAO’s recommendations into ‘the governance for the Defence estate’. Defence informed the Committee that the broader estate strategy is close to being finalised and that it draws on material already available, such as the White Paper, which identifies five principles linked to basing of Defence.[28]
4.33 Mr Simon Lewis, Deputy Secretary Defence Support informed the Committee of his position as chair of the Defence Estate Performance and Investment Committee. Mr Lewis outlined that the committee’s deliberations on the condition of the estate:
…will draw on these recommendations very specifically to help make choices about how we allocate scarce dollars.[29]
4.34 Defence advised that while it had a ‘widely dispersed and ageing estate’, the Department is also investing heavily to review parts of the estate (with over $1 billion invested in its capital program). Defence identified the challenge of consolidating the estate with new investment facilities sitting alongside aged facilities and recognised the need for an overarching management program.[30]
4.35 Following these comments, the Committee suggested that in an ‘environment of rationalisation’ a difficult part of Defence’s decision‑making must be ‘political management and expectation management at a community level’. The Committee asked Defence how it would engage with these complicated issues.
4.36 Defence replied that while undoubtedly it is a challenge to re-shape the defence forces, noting the impact of ‘local politics’, they have been scoping options for a rationalised estate footprint. This work on estate consolidation is being fed into processes for the Defence Force Posture Review.[31]
4.37 The ANAO assessed that Defence’s approach to estate maintenance planning was not ‘fully effective’ and recommended that Defence improve its planning for estate maintenance through a series of activities, including:
4.38 The Committee asked what steps Defence had taken to implement the ANAO’s recommendation and how this work was associated with Defence’s broader reform activities.
4.39 Defence outlined that it was investing in more work to gain a better ‘understanding of the current standard of infrastructure’ across the estate. Specifically, the Department was conducting a review of its Infrastructure Appraisal process which aims to provide more robust information to decision makers by enhancing the ‘quality and consistency’ of the appraisal process. The review will specifically consider the suitability of specialist advice to improve the ‘collection and assessment of information on the condition, utilisation and contribution to defence capability’.[34]
4.40 The Committee was interested in the timeframes for the review as well as the number of proposed tender rounds, and Defence’s plans following the completion of the assessments.
4.41 Defence advised that the review was expected to be completed by June 2012.[35] Further, the Department confirmed that the first round of tenders was in the market and that the target for procuring a provider and putting in place the necessary contracts was mid-to-late November.[36]
4.42 Regarding the tender round, Defence outlined that in the first instance their approach focused on obtaining a national project manager with the technical expertise to provide:
4.43 Defence advised that once contracts for these services were in place, due to the size of the program the Department may consider appointing others to assist. Defence indicated that these engagements may occur through a ‘hierarchy of contracting arrangements’.[38] The Department advised that these decisions depend on the outcome of the first tender round.
4.44 In Defence’s discussions regarding its procurement of expert advisers, the Department raised that it was also undertaking detailed assessments of engineering services at a range of bases. While Defence highlighted that this was a progressive program (with all key bases to be assessed by 2015), it informed the Committee that it had commenced a project to conduct ‘baseline assessments of the condition of engineering services’ provided at seven key bases.[39]
4.45 The Committee surmised that in essence Defence was driving its response to the ANAO’s recommendation through ‘contracting out to qualified specialist staff’. Defence responded that specialist advice was identified as a priority need, particularly in the context of the Department’s limited internal resources.[40]
4.46 Defence, in its opening statement acknowledged that additional funding may be needed to maintain the estate in line with required standards. However, the Department noted that funding for estate maintenance was to be considered alongside other priorities and that Defence allocates funding on an ‘opportunity basis’. Defence pointed to the development of the Defence estate strategy, which will provide the ‘strategic direction for use and management of the estate’.[41]
4.47 The ANAO’s examination of maintenance services delivered under the CMS contracts revealed mixed performance.[42] The audit identified the key weakness in the two sub‑regions with unsatisfactory performance was the ‘contractors’ inability to deliver the full Risk Managed Works program’.[43]
4.48 With the current CMS contracts due to expire at the end of 2011, the ANAO recommended that Defence review its approach to estate maintenance delivery to ‘focus on the outputs that Defence requires’. Building on this, the ANAO recommended Defence:
4.49 Defence informed the Committee that in response to the ANAO’s recommendation, the Department had completed the first stage of its contracting model review.[45] The Department outlined that Stage 1 involved:
…a review of the current contractual arrangements against industry-leading practice and consultation with current and prospective industry providers to inform the development of options that best represents defence requirements and be industry aligned.[46]
4.50 Stage 1 culminated at the Defence and industry conference on 28 June 2011, with three proposed ‘bundling options’ presented for the delivery of maintenance services. Defence advised the next stage was to evaluate each option, pick the preferred option and develop an appropriate approach. The Department also highlighted that to help with the decision making process, it was consulting with industry to develop the most suitable option for Defence to deliver maintenance services over the next three to five years. This includes better alignment with industry and developing its approach to market in 2012.[47]
4.51 The ANAO noted the tension between the saving and non-saving stream classifications for the Defence estate under the SRP. Within the program, the Defence estate is designated as a non‑savings stream, while estate maintenance is classified as a savings stream. Within this context, the impact of the SRP on the estate’s longevity was ‘unclear’ to the ANAO, particularly as savings of $500 million in estate maintenance were to be achieved over a ten year period.[48]
4.52 The Committee asked Defence to explain the rationale behind the savings and non-savings categories for the estate and estate maintenance. Defence responded by expressing that while estate consolidation would lead to long-term savings, there are ‘significant timing issues’ regarding savings in this area. Mr Lewis acknowledged that while the program preceded his time at Defence, he understood that the architects of the program recognised the upside of pursuing consolidation. However, it was also noted that it would not be a stream ‘likely to achieve any significant savings’ within the SRP’s timeframe (closing in 2020).
4.53 Defence highlighted that in the short term more investment is needed to manage the transition to a consolidated estate. Defence pointed to the funds needed to create and dispose of facilities, particularly as sites that are to be closed are likely to need ‘significant remediation’. Considerable site remediation is common within the Defence estate space and Defence cited the current case at Maribyrnong, along with others in the past.[49]
4.54 As outlined in the ANAO’s report, there are shortcomings in the Defence Estate Management System (DEMS) currently used by staff to plan and deliver estate maintenance. The ANAO cited that Defence considered there were underlying weaknesses in the system regarding ‘data quality and reliability’. Further, regular users of DEMS interviewed by the ANAO commented on system deficiencies such as its slow operating pace and raised concerns regarding the ‘quality and integrity of data stored’ in the system.[50]
4.55 During the audit the ANAO became aware that Defence was developing a replacement system the Garrison and Estate Management System (GEMS), expected to be completed in early 2013. The Department informed the ANAO that the new system would rectify some of the current issues and recognised the need to cleanse existing data to improve data quality prior to transfer into GEMS.[51]
4.56 The Committee asked Defence how its broader activities to improve planning for estate maintenance fit with the move to GEMS.[52] Defence explained that GEMS is the new IT system planned to support the management of the estate and would provide:
4.57 The Department highlighted that this system would provide better access to ‘real-time data’ to enable enhanced management of the estate. Defence noted that this was particularly important in the context of the ‘harmonised legislation’ [Model Work Health and Safety Act][54] to be implemented on 1 January 2012.[55]
4.58 As outlined in the audit report, Defence’s prioritisation of maintenance works is focused on ‘maintaining significant Defence operational capabilities’. Each item of proposed work is also prioritised, with the highest priority given to works that would result in a breach of the Occupational Health and Safety Act 1991 if not completed within the year.[56] Further, the audit identified that adequate information relating to a number of elements including:
…satisfaction of OH&S requirements is required by decision makers when considering the level and distribution of resources for estate maintenance.[57]
4.59 In response to the linkages draw by Defence, the Committee inquired how the Department was going to align its mid-June Defence estate strategy with the newly introduced health and safety arrangements. The Department told the Committee that it took the safety of its employees ‘very seriously’ and pointed out that managing risk and safety is already part of their daily business in their hundreds of locations and tens of thousands of buildings.[58]
4.60 Defence acknowledged though, that the new legislation created further motivations for the Department to make improvements, noting that:
The improvements that we are talking about are a multi-year challenge for us. We have to deal with safety in the workplace today and also deal with improving our systems, organisational arrangements and governance over a period of time.[59]
4.61 The Committee is conscious of the contribution of the defence estate and the maintenance of its facilities to the wider defence force capability. Adequate funding, effective planning, robust management systems and high performing delivery of maintenance services are important to ensure the estate is maintained to required standards.
4.62 In considering the ANAO’s report and evidence provided, the Committee remains concerned by the ANAO’s findings of shortcomings in Defence’s planning and delivery of maintenance services, and issues raised regarding funding shortfalls.
4.63 The Committee strongly supports the ANAO’s recommendations and views the implementation of these recommendations by Defence as essential in order to drive improvements in Defence’s planning and delivery of estate maintenance, as well as to help curtail further decline of the estate’s useful life.
4.64 The Committee recognises the reform programs and reviews Defence is presently conducting. The Committee also acknowledges the Department’s efforts to incorporate the implementation of the ANAO’s recommendations within the development and execution of a wider Defence estate strategy. The Committee sees the development of a Defence estate strategy as an essential tool to provide better strategic direction for the overall management of the estate, including maintenance planning and delivery.
4.65 While Defence advised of a number of major reviews and new activities to support the implementation of the ANAO’s recommendations, the Committee notes these were still in the early stages. In light of this, the JCPAA wishes to see the timely completion of these activities and the subsequent full implementation of the ANAO’s recommendations. The Committee therefore expects Defence to report back to demonstrate this has been achieved.
Recommendation 3 |
|
Due to concerns raised by the Joint Committee of Public Accounts and Audit in regard to implementation timelines, the Committee recommends that following the tabling of this report, the Department of Defence provide updates on the implementation of the ANAO’s recommendations as follows:
The reports to the Committee should address each recommendation and demonstrate how the outcomes of the reform, and review activities underway, have contributed to the implementation of the ANAO’s recommendations. |
|